Hi Team,
I need your advice:
I have a dual-site MAESTRO (2pcs MHP140, 4 pcs CP6500). The CP6500 are end-of-life soon.
The new SGMs are CP9300. I know the mix-and-match does not work between this types.
What would be the most effective process of the change from the downtime point of view?
Have somebody done such kind of changes already? If yes, what was the experience? Please share with me.
I have two scenario:
- I delete, then rebuild the Security Group -> this is the last what would I do
- I put the CP9300 next to the two CP6500 -> if the config arrives to the CP9300, I remove the two 6500, then
I don't want to do it without outage, because it is impossible, but I want to cause as short outage as is can.
Every answer would be very appreciated!
Akos
----------------
\m/_(>_<)_\m/