R80.30 JHF #3 - New Ongoing Take #71

Hi all,

A new Ongoing Jumbo Hotfix Accumulator take for R80.30 (Take #71) is available.

Please refer to sk153152.

 

Please note the following:

  • The new release will be mention in the JHF sk153152.
  • This new release of R80.30 Jumbo Hotfix Accumulator take #71 can be installed on both Gaia 2.6.18 (based on R80.30 GA Take 200) and Gaia 3.10 (based on R80.30 3.10 GA Take 300).
  • The new release will not be published via CPUSE as a recommended version.
  • Availability:

o   Will be provided by customer support

o   Available for download via CPUSE by using package identifier.

 

Thanks,

RLM Group

 

 

4 Replies

Re: R80.30 JHF #3 - New Ongoing Take #71

According to sk153152:

To install Take 71 on devices using Take 50, manually uninstall of Take 50 is required.

Any reason for that, i thought such obstacles are only part of CPUSE history ?

0 Kudos
Employee+
Employee+

Re: R80.30 JHF #3 - New Ongoing Take #71

Hi,

We are going to address this issue in the next few days, meanwhile if you already installed Take 50 and you would like to install Take 71, you are request to uninstall Take 50 prior installing Take 71.

sorry for the inconvenient,

it is temporary.

Thanks,

Shirley.

0 Kudos

Re: R80.30 JHF #3 - New Ongoing Take #71

Such a short list of resolved issues between take 50 and 71...
Employee+
Employee+

Re: R80.30 JHF #3 - New Ongoing Take #71

Indeed long list but be aware that it  includes: fixes already done in new appliances to better support large numbers of cores; fixes already done to improve linux 3.10 kernel; fixes added in recent R80.20 jumbo

So the long list is good sign of “house cleaning” and not a bad indication on R80.30 quality - on the contrary, now that its all one jumbo flavor, you can get the fixes more effectively 